When the Rolling Hills Estates City Council approved 90 apartments at Peninsula Center in December 2024, how much closer did that bring a construction fence on Norris Center Drive?
Less than the vote suggested. Nearly two years later, the 7,000-square-foot vacant building on the site is still the most visible part of the project. A second, much larger proposal on Deep Valley Drive is still in environmental review. If you are comparing Peninsula neighborhoods and looking at homes near the city's commercial core, the approval dates in old headlines won't help you much. The more useful signals come later: a building permit application and a public hearing date. Neither project has reached its next one yet.
The 90 Units at 27525 Norris Center Drive
The Residences at Peninsula Center is a proposal from Vestar, the Phoenix-based company behind the shopping center. It sits on a 2-acre portion of the center at 27525 Norris Center Drive. The plan calls for removing the vacant 7,000-square-foot building and putting up a five-story podium structure with a maximum height of 68 feet. All 90 units would be rentals: 57 one-bedrooms and 33 two-bedrooms, with 9 reserved for moderate-income households. The project includes 240 parking spaces, and 85 of them would be shared public and private parking on the ground floor.
Its approval was not simple. The Rancho Palos Verdes Border Issues Status Report tracks projects near that city's boundary, and its July 7, 2026 update lays out the sequence:
- March 14, 2023. The City Council received a first-look presentation.
- March 12, 2024. The Council found that the proposed community benefits qualified the project for bonus-level development.
- July 9, 2024. The city rezoned its entire Commercial District to Commercial General Mixed-Use.
- August through October 2024. The Planning Commission held hearings on August 5, September 3 and October 7 but could not agree on a recommendation, so it made none.
- November 12 and December 10, 2024. The Council approved the development applications, then gave the development agreement its second reading.
- June 2025, December 2025, July 2026. At each check-in, Rolling Hills Estates planning staff reported that the developer had not yet applied for building permits.
On the city's development project updates page, the project's status still reads "Entitlements Approved by City Council on December 10, 2024." As of the July 2026 report, that approval was about 19 months old and no permit application had followed it.
Why an Approved Project Can Sit Still
The answer is mostly arithmetic, and it applies across the region. In a September 22, 2026 report, the Los Angeles Times cited Kidder Mathews data showing the average sale price per unit in L.A. County multifamily buildings fell from $397,289 in 2022 to $280,591 in 2026. That roughly 30% drop changes the decision for any developer holding an approval. An apartment building is financed against its expected value when finished. When that value falls while borrowing costs rise, the same approved plans stop producing a return.
In the same Times report, Kidder Mathews executive vice president Darin Beebower describes the mood among builders:
"Most developers I speak to are 'pencils down.' And they have been for a while."
The Times also cites the rate gap: margins shrink considerably when developers borrow at 7% instead of 2%. It reports that about 25,636 apartment units were under construction county-wide in the first half of 2026, around 15% fewer than a year earlier. Some causes the article discusses, such as the City of Los Angeles transfer tax known as Measure ULA, apply only inside L.A. city limits, not in Rolling Hills Estates. Interest rates and construction costs apply everywhere.
Costs were already high before rates moved. A RAND study published in April 2025 found that market-rate multifamily construction in California cost about 2.5 times as much per square foot as in Texas, and took more than 22 months longer to complete. A Terner Center report from September 2026 adds that impact fees can affect whether a project is feasible, and that paying them early in development can raise carrying costs.
None of these sources explains Vestar's timing at Peninsula Center specifically, and the company's reasons are not on the public record. What the regional numbers do show is that a 90-unit rental building approved in late 2024 was approved just as apartment values in the county were falling. Approvals also don't last forever. In an August 2026 analysis, the Center for Public Enterprise estimates that land-use entitlements typically expire after two to three years. That is a general estimate, not a statewide rule. The specific terms for this project are in its development agreement, which California Government Code Section 65865.2 requires to state its duration.
Brickwalk Is Running on a Different Clock
The Brickwalk Residences proposal from Rolling Hills Capital, LLC is roughly five times larger. It covers five lots on 10.42 acres at 615–855 Deep Valley Drive and 924–950 Indian Peak Road. The current plan has 454 units, 10,229 square feet of commercial space and 881 parking spaces in four buildings. Three buildings along Deep Valley Drive would be seven stories, and the one on Indian Peak Road would be five. According to the city's project page, the 44 units for very low-income households qualify the project for mandatory benefits under California's Density Bonus Law, and the page links to state-level overviews of that law. At the January 2024 first-look meeting, the proposal was for 407 units.
The two projects follow different rules about timing. The Residences has its approval and is waiting on the developer. Brickwalk is still waiting on the city's review, but its applicant filed an SB 330 preliminary application on February 7, 2024, followed by the full development application on August 5, 2024.
Then state law changed partway through review. On June 24, 2025, the City Council approved a contract for a Supplemental Environmental Impact Report, plus a third-party geotechnical peer review. A week later, Assembly Bill 130 and Senate Bill 131 took effect on July 1. They narrowed environmental review for infill housing and applied to pending applications. The city concluded that Brickwalk appears to qualify for an exemption. It proposed a narrow review of habitat for certain protected species, and the applicant agreed. On November 18, 2025, the Council replaced the Supplemental EIR with revised contracts for a more limited Addendum. The Rancho Palos Verdes report notes that this review will involve less public outreach than the fuller report would have. Rolling Hills Estates planning staff has been coordinating with Rancho Palos Verdes, and as a result two Crenshaw Boulevard intersections were added to the traffic study: Indian Peak Road and Crestridge Road.
As of July 2026, the Addendum was not expected to reach the Rolling Hills Estates Planning Commission until late 2026 or early 2027. It was not on the October 5 Planning Commission agenda. That meeting's business item was a minor remodel at 3B Peninsula Center, and the next meeting is set for Monday, November 2, at 7 p.m. The October 13 City Council public hearing covered citywide zoning amendments, not either housing project.
The Two Projects Side by Side
| The Residences at Peninsula Center | Brickwalk Residences | |
|---|---|---|
| Applicant | Vestar | Rolling Hills Capital, LLC |
| Site | 27525 Norris Center Drive | 615–855 Deep Valley Dr., 924–950 Indian Peak Rd. |
| Units | 90 rentals, 9 moderate-income | 454, including 44 very low-income |
| Height | Five stories, 68 ft. max | Three seven-story buildings and one five-story building |
| Status | Entitled Dec. 10, 2024 | Development and environmental review |
| Waiting on | A building permit application from the developer | An Addendum hearing at the Planning Commission |
| Last dated update | No permit application as of July 2026 | Hearing expected late 2026 or early 2027 |
Together, the two projects account for 544 units on paper. Neither is under construction, and each is stalled for a different reason. The Residences depends on whether the numbers work for its developer. Brickwalk depends on the city's review calendar.
Meanwhile, the Shopping Center Keeps Leasing
The retail center around the Residences site has kept signing tenants. According to Peninsula Shopping Center, Monarch Ink, a children's boutique, is open next to Baskin-Robbins. The center also advertised an October 28 opening for Canaan Chinese Cuisine, next to MOD Pizza. These are ordinary leasing decisions made under current conditions. For the next few seasons, the parking lots and storefronts near Norris Center Drive will likely look much the same as they do now.
A Few Common Questions
When will construction start at Peninsula Center? No start date has been announced. A building permit application from Vestar would come first, and none had been filed as of the July 2026 update.
Can the public weigh in on Brickwalk? The Addendum is expected at a Planning Commission meeting in late 2026 or early 2027. The city posts agendas ahead of each meeting, and the project page lists the Planning Division's contact.
Does the Residences approval expire? That depends on the terms of its development agreement, which are not summarized on the city's project page. This post is general information, not legal or financial advice. Before relying on a timeline, check the city's records and talk with the right professional.
If you are weighing a home near Deep Valley Drive or Norris Center Drive and want to know how these projects could affect your timing, Gayle Probst can go through the latest city filings with you. Schedule a complimentary market consultation, or call Gayle for a free home valuation.